PROJECT OVERVIEW
PROJECT NO | JAD 14002 |
CLIENT | ADNOC GAS PROCESSING (GASCO) |
Client Contract No | PROJECT NO.600512 (GES 2012-2015) |
MAN-HOURS | 5950 |
PROJECT TITLE | UPGRADING OF SUBSTATION·19 AT MAQTA FEED AND DETAIL STUDY-SS·19 |
SCOPE OF WORK | FEED ENGINNERING FOR UPGRADTION OF SUBSTATION AT MAQTA, EPC COST ESTIMATION, EPC SCOPE OF WORK, EPC TENDER PACKAGE |
BRIEF SCOPE OF WORK & LIST OF DELIVERABLES | |
GENERAL
EPC COST ESTIMATE REPORT EPC SCOPE OF WORK EPC TENDER PACKAGE PROJECT DESIGN BASIS PROJECT DEFINITION REPORT PROJECT SPECIFICATIONS ADDENDUMS ADEQUACY CHEQYE REPORTS FOR SUB STATION SUB STATIONS LAY OUT DARWINGS SPECIFICATION, DATA SHEETS, MR’S FOR HV/ LV CABLES, UPS, MV/LV SWITCH GEARS ELECTRICAL LOAD LIST, SLD, MTO, SCHEDULES HEAT DISSPIATION , POWER SYSTEM STUDY REPORTS HSE PLAN, HSE PHIOLOSOPHY, HAZID /ENVID/ OHRA SCOPE OF WORK HAZID /ENVID/ OHRA CLOSE-OUT REPORT CONSTRUCTABILITY REVIEW HAZARDS & EFFECTS REGISTER HVAC COOLING LOAD CALCULATIONS SPECIFICATION ADDENDUM HVAC DUCTWORK AND INSULATION HVAC COOLING LOAD CALCULATIONS HVAC CONTROL SYSTEMS SPECIFICATIONS SUBSTATION-19 HVAC SCHEMATIC DIAGRAM |
|
HVAC COOLING LOAD CALCULATIONS
HVAC CONTROL SYSTEMS SPECIFICATIONS HVAC TESTING, ADJUSTING & BALANCING (TAB) SPECIFICATIONS INSTRUMENT INDEX, I/O LIST, ALARM & TRIP SCHEDULE, SPECIFICATIONS, DATA SHEETS, & MR’S FOR FOC , CABLES, JUNCTION BOX , FIRE AND GAS DEVICES, FIRE ALARM SYSTEM ARCHITECTURE DRAWING, FIRE & GAS CABLE BLOCK DIAGRAM SCOPE OF WORK FOR MODIFICATION OF SMC SYSTEM F&G INSTRUMENT INDEX |
- Project Name UPGRADING OF SUBSTATION•19 AT MAQTA FEED AND DETAIL STUDY-SS•19
- Client ADNOC GAS PROCESSING (GASCO)
- Category FEED & DETAIL ENGINEERING