JAD-12003_DE

PROJECT OVERVIEW

PROJECT NO JAD 12003
CLIENT ADNOC GAS PROCESSING (GASCO)
Client Contract No TP.11.096
MAN-HOURS 32500
PROJECT TITLE EPC FOR PROCUREMENT & INSTALLATION OF NGL PIPELINES PUMPS

124-G-602 A/B) AT ASAB-O AND ALLIED WORKS

SCOPE OF WORK DETAIL ENGINEERING FOR EPC PROJECT, INCLUDES 2 NGL PUMPS INSTALLATION, NEW SUBSTATION, DCS MODIFICATION & EXISTING PUMPS DEMOLITION
BRIEF SCOPE OF WORK & LIST OF DELIVERABLES
PROEJCTS: – PROJECT DESIGN BASIS, PDS MODELLING PROCEDURE 3D MODEL REVIEW, SITE VISIT REPORTs, PROJECT EXECUTION, COORDINATION AND QUALITY PLAN. PROCUREMENT & CONSTRUCTION MANAGEMENT
PROCESS:- LINE SCHEDULE, EQUIPMENT SCHEDULE, PROCESS DESCRIPTION, STEADY STATE HYDRAULIC CALCULATION REPORT, SURGE ANALYSIS REPORT, UTILITY CALCULATION REPORT, DYNAMIC SIMULATION STUDY REPORT, ISOLATION, VENT AND DRAIN PHILOSOPHY, OPERATING AND CONTROL PHILOSOPHY, PRE-COMMISSIONING AND COMMISSIONING PHILOSOPHY, TIE-IN PHILOSOPHY, DEMOLITION DRAWINGS
PIPING /PIPELINE  :- PIPING STRESS ANALYSIS, GAD, MTO FOR PIPING BULK, PIPING TIE-IN SCHEDULE, SPEICIFCATIONS, DATA SHEETS, MR, TBE FOR PIPING BULK, VALVES, DEMOLITION
MATERIAL & CORROSION :- MATERIAL SELECTION & CORROSION CONTROL PHILOSOPHY, CATHODIC PROTECTION PHILOSOPHY REPORT, CATHODIC PROTECTION SPECIFICATION, MATERIAL SELECTION REPORT, CATHODIC PROTECTION CALCULATIONS
MECHANICAL :- MR’S, SPECIFICATION, DATA SHEETS ,TBE FOR NGL PUMPS & MOBILE CRANES ,SURGE BULLET VESSEL MODIFICATION INCLUDES ASME REQUIREMENTS,  HVAC SYSTEM
CIVIL:- PUMPS FOUNDATION, SHELTER, HVAC SYSTEM FOUNDATION, NEW 11KV SUBSTATION MATERIAL TAKE OFF , PIPE SUPPORTS, PIPE RACK MODIFICATION, DEMOLITION DRAWINGS
ELECTRICAL :- NEW 11KV SUBSTATION & MOTORS FOR NGL PUMPS,  TIE-IN SCHEDULE, MTO FOR ELECTRICAL BULK MATERIAL, CABLE SCHEDULE, EQUIPMENT SCHEDULE, JUNCTION BOX SCHEDULE, LIGHTING CALCULATION, SPECIFICATIONS, DATA SHEETS,TBE AND MR’S  FOR 11KV MV/ 415 V LV SWITCH GEAR, IPCS MOTORS, TRANSFORMERS, UPS,, CONTROL AND EARTHING CABLES, MOV POWER DISTRIBUTION BOARD, FOR ELECTRICAL BULK MATERIALS, ELECTRICAL LOAD LIST, POWER SYSTEM ADEQUACY CHECK REPORT, CABLE SIZING CALCULATION, DEMOLITION DRAWINGS
TELECOMMUNICATION:- SPECIFICATIONS, DATA SHEETS, & MR’S  FOR CCTV SYSTEM,PA, TELEPHONE FOC,CCTV, MTO. CABLE SCHEDULE, JUNCTION BOX SCHEDULE
INSTRUMENTATION & CONTROL:- INSTRUMENT INDEX, I/O LIST, ALARM & TRIP SCHEDULE, SPECIFICATIONS, DATA SHEETS, TBE & MR’S  FOR CONTROL VALVES , SHUT DOWN VALVES, PRESSURE GAUGE, PRESSURE TRANSMITTER, CABLES, JUNCTION BOX, FLOW TRANSMITTER , MTO, SOW FOR EXISTING DCS / RTU SYSTEM MODIFICATION
HSE :- HSE PLAN, HSE PHILOSOPHY, HAZARDOUS ARE CLASSIFICATION SCHEDULE, PLOT PLAN REVIEW AND CLOSE-OUT REPORT, SAFETY EQUIPMENT DATA SHEET SAFETY SHOWER AND EYEWASH STATION, HSE ACTION TRACKING REGISTER, SOW FOR HAZOP, HAZID,SIL VERIFICATION AND VALIDATION, F&G MAPPING STUDY & SIMOPS, PHSER, CONSTRUCTABILITY Review AND CLOSE OUT REPORTS.