JAD-10003_DE

PROJECT OVERVIEW

PROJECT NO JAD 10003
CLIENT ADNOC REFINING (TAKREER)
MAN-HOURS 29550
PROJECT TITLE ISOMERATE QUALITY IMPROVEMENT – PROJECT NO. 5625

ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING(EPC) WORKS

SCOPE OF WORK DETAIL ENGINEERING FOR EPC PROJECT, PROCUREMENT & CONSTRUCTION
BRIEF SCOPE OF WORK & LIST OF DELIVERABLES
PROEJCTS: – PROJECT DESIGN BASIS, PDS MODELLING PROCEDURE 3D MODEL REVIEW, SPI,

SP P& ID, SP3D, SITE VISIT REPORTs, PROJECT EXECUTION, COORDINATION AND QUALITY PLAN. PROCUREMENT & CONSTRUCTION MANAGEMENT

PROCESS:- LINE SCHEDULE, EQUIPMENT SCHEDULE, PROCESS DESCRIPTION, STEADY STATE HYDRAULIC CALCULATION REPORT, SURGE ANALYSIS REPORT, UTILITY CALCULATION REPORT, DYNAMIC SIMULATION STUDY REPORT, ISOLATION, VENT AND DRAIN PHILOSOPHY, OPERATING AND CONTROL PHILOSOPHY, PRE-COMMISSIONING AND COMMISSIONING PHILOSOPHY, TIE-IN PHILOSOPHY, DEMOLITION DRAWINGS
PIPING /PIPELINE  :- PIPING STRESS ANALYSIS, GAD, MTO FOR PIPING BULK, PIPING TIE-IN SCHEDULE, SPEICIFCATIONS, DATA SHEETS, MR, TBE FOR PIPING BULK, VALVES, DEMOLITION
MECHANICAL: – MR’S, SPECIFICATION, DATA SHEETS, TBE FOR PUMPS, MOBILE CRANES, VESSELS, SKID PCAKAGES, HEAT EXCHANGERS.
CIVIL:- PUMPS FOUNDATION, SHELTER, HVAC SYSTEM FOUNDATION, NEW 11KV SUBSTATION MATERIAL TAKE OFF , PIPE SUPPORTS, PIPE RACK MODIFICATION, DEMOLITION DRAWINGS
ELECTRICAL :- TIE-IN SCHEDULE, MTO FOR ELECTRICAL BULK MATERIAL, CABLE SCHEDULE, EQUIPMENT SCHEDULE, JUNCTION BOX SCHEDULE, LIGHTING CALCULATION, SPECIFICATIONS, DATA SHEETS,TBE AND MR’S  FOR  SWITCH GEAR, , MOTORS, TRANSFORMERS, UPS, CONTROL AND EARTHING CABLES, MOV POWER DISTRIBUTION BOARD, FOR ELECTRICAL BULK MATERIALS, ELECTRICAL LOAD LIST, POWER SYSTEM ADEQUACY CHECK REPORT, CABLE SIZING CALCULATION, DEMOLITION DRAWINGS
TELECOMMUNICATION:- SPECIFICATIONS, DATA SHEETS, & MR’S  FOR CCTV SYSTEM,PA, TELEPHONE FOC,CCTV, MTO. CABLE SCHEDULE, JUNCTION BOX SCHEDULE
INSTRUMENTATION & CONTROL:- INSTRUMENT INDEX, I/O LIST, ALARM & TRIP SCHEDULE, SPECIFICATIONS, DATA SHEETS, TBE & MR’S  FOR CONTROL VALVES , SHUT DOWN VALVES, PRESSURE GAUGE, PRESSURE TRANSMITTER, CABLES, JUNCTION BOX, FLOW TRANSMITTER , MTO, SOW FOR EXISTING DCS / RTU SYSTEM MODIFICATION
HSE :- HSE PLAN, HSE PHILOSOPHY, HAZARDOUS ARE CLASSIFICATION SCHEDULE, PLOT PLAN REVIEW AND CLOSE-OUT REPORT, SAFETY EQUIPMENT DATA SHEET SAFETY SHOWER AND EYEWASH STATION, HSE ACTION TRACKING REGISTER, SOW FOR HAZOP, HAZID,SIL VERIFICATION AND VALIDATION, F&G MAPPING STUDY & SIMOPS, PHSER, CONSTRUCTABILITY Review AND CLOSE OUT REPORTS.
  • Project Name ISOMERATE QUALITY IMPROVEMENT - PROJECT NO. 5625 ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING(EPC) WORKS
  • Client ADNOC REFINING (TAKREER)
  • Category FEED & DETAIL ENGINEERING